All space in all active log data sets has been used because of delays in offload processing. The PowerExchange Logger cannot continue processing.
The log manager waits for an available data set.
Use a DISPLAY OBJECT=LOG command to verify that no outstanding requests related to the log offload process exist. Respond to any outstanding requests and then permit the offload process to continue. If the delay was caused by lack of resources for the offload process, you must make the resources available so that the offload process can complete. The PowerExchange Logger can then resume processing.